Abilene campus (Stargate flagship)

Crusoe · Abilene, Texas

Crusoe's June 9, 2026 release says the first two buildings of this Abilene campus are operational and six more are under construction. The planned campus is eight buildings and 1.2 GW. Crusoe, Blue Owl and Primary Digital describe a $15 billion joint venture to fund it, and a March 2026 Crusoe release expects the six added buildings to be finished by the end of 2026. Our build label follows the June release and its date. Later progress figures have been reported elsewhere, and we have not found a company release or filing for them, so they are not on this card. A separate 900 MW campus next door for Microsoft has its own card, because it is not part of this 1.2 GW.

  1. Planned or site prep
  2. Under construction
  3. Partly operating
  4. Operating
Build progress
Partly operatingCompany-reported

“the first two buildings are operational and an additional six buildings are under construction” Crusoe release: contracted capacity approaches 5 GW (June 9, 2026)

Financing
Financing announcedCompany-reported

“announced today the second phase of a $15 billion joint-venture to fund the 1.2 gigawatt AI data center in Abilene, Texas” Crusoe, Blue Owl and Primary Digital release: $15 billion joint venture (May 21, 2025)

Planned capacity
1.2 GW across eight buildings

“bringing the total facility to eight buildings, approximately 4 million square feet, and a total power capacity of 1.2 gigawatts (GW)” Crusoe release: Abilene campus expands to 1.2 GW (March 18, 2025)

In service
Not established
Announced investment
$15 billionCompany-reported
Joint venture of Crusoe, Blue Owl Capital and Primary Digital Infrastructure to fund the 1.2 GW campus. A company's announced commitment to a project, often over many years. A pledge, not money spent or a building built.

“second phase of a $15 billion joint-venture to fund the 1.2 gigawatt AI data center in Abilene, Texas” Crusoe, Blue Owl and Primary Digital release: $15 billion joint venture (May 21, 2025)

Next thing to watch
The remaining six buildings being finished, which Crusoe's March 2026 release expects by the end of 2026.

“is expected to reach completion by the end of 2026” Crusoe release: new 900 MW Abilene campus for Microsoft (March 27, 2026)

Sources

No Nexairi story linked yetLast reviewed Nov 24, 2026. Facts only.

Change history

Newest first. We never edit or delete an entry. When we re-read a source and correct ourselves, that gets its own entry, marked as our label changing, not as news from the site.

  1. Nov 24, 2026 · Checked, no change

    Re-checked against Crusoe's June 9, 2026 release: first two buildings operational, six under construction. Build label unchanged.

    Crusoe release: contracted capacity approaches 5 GW (June 9, 2026)
  2. Nov 24, 2026 · Added

    Added as Partly operating, financing announced. Status is as of the September 30, 2025 release.

More Crusoe sites

Other sites in Texas

See Abilene campus (Stargate flagship) on the globe with all 36 sites

Cite this

Nexairi, "Abilene campus (Stargate flagship) (Crusoe)," AI Infrastructure Project Directory, last reviewed Nov 24, 2026. https://nexairi.com/on-the-record/directory/crusoe-abilene-stargate-flagship/

How labels are set: How we verify. Found a mistake? Tell us. Fixes are logged on the corrections page. Facts only. Not investment advice. Data is CC BY 4.0.