Project Matador
Fermi America · Carson County, TexasSite preparation has started, but Fermi says building the data centers waits on a signed tenant lease and permission to proceed from Texas Tech, its landlord for the site. Its first tenant lease, with TensorWave, ended on Nov. 10. The same day Fermi signed a non-binding letter of intent with an unnamed hyperscaler for about 600 MW.
- Planned or site prep
- Under construction
- Partly operating
- Operating
- Build progress
- Planned or site prepCompany-reported
- Financing
- Not established
- Planned capacity
- About 11 GW of on-site power generation, planned (power, not data center load)
- In service
- Not established
- Next thing to watch
- Texas Tech's notice to proceed. Without it by year-end, the lease can be ended.
“Preliminary site development commenced in 2025, and vertical construction is expected to commence following the closing of a definitive tenant lease” Fermi 10-Q (Sept. 30, 2026)
“integrating approximately 11 GW of private-grid power generation with large-scale AI data center infrastructure” Fermi 10-Q (Sept. 30, 2026)
“the Company must receive a notice to proceed from TTU by December 31, 2026, and TTU may terminate the lease if the notice is not received by that date” Fermi 10-Q (Sept. 30, 2026)
Sources
- Fermi 10-Q (Sept. 30, 2026) (SEC filing)
- Fermi 8-K (Nov. 23, 2026) (SEC filing)
On the Record
- Nov 23, 2026 8-K: Other
- Nov 12, 2026 10-Q: Reported
- Nov 12, 2026 8-K: Reported
Change history
Newest first. We never edit or delete an entry. When we re-read a source and correct ourselves, that gets its own entry, marked as our label changing, not as news from the site.
Nov 24, 2026 · Changed on the ground
Logged from Fermi's Nov. 23 8-K (Item 8.01): the obligations under the customer prepay agreement discussed on its previous earnings call have been fulfilled, and the amounts due have been funded. The filing gives no amount, does not name the customer, and does not say the agreement relates to Project Matador. We have not read the earnings call. Build progress and financing labels are unchanged. The open item is still the Texas Tech notice to proceed.
Fermi 8-K (Nov. 23, 2026)Nov 17, 2026 · Changed on the ground
Logged on re-reading the 10-Q: the TensorWave tenant lease ended on Nov. 10, and Fermi signed a non-binding letter of intent with a hyperscaler for about 600 MW. This happened before our first review; we missed it then. Build progress and financing labels are unchanged.
Fermi 10-Q (Sept. 30, 2026)Nov 17, 2026 · Our label changed
Label renamed to Planned or site prep, because site preparation has begun. Nothing new happened at the site.
Fermi 10-Q (Sept. 30, 2026)Nov 16, 2026 · Added
Added as Announced.
Other sites in Texas
- Childress campus (Horizons 1 to 4)IREN · Childress, Texas · Partly operating
- Sweetwater 1IREN · Sweetwater, Texas · Under construction
- Sweetwater 2IREN · Sweetwater, Texas · Planned or site prep
- Black Pearl FacilityCipher Digital · Wink, Texas · Partly operating
- Barber Lake data centerCipher Digital · Colorado City, Texas · Under construction
- Abernathy HPC Campus (joint venture)TeraWulf · Abernathy, Texas · Not established
See Project Matador on the globe with all 36 sites
Cite this
Nexairi, "Project Matador (Fermi America)," AI Infrastructure Project Directory, last reviewed Nov 24, 2026. https://nexairi.com/on-the-record/directory/fermi-project-matador/
How labels are set: How we verify. Found a mistake? Tell us. Fixes are logged on the corrections page. Facts only. Not investment advice. Data is CC BY 4.0.