Austin data center

Core Scientific · Austin, Texas

Core Scientific says lease operations at Austin began in the second quarter of 2024, under a February 2024 contract with CoreWeave for 16 MW. This is the smallest of its CoreWeave sites. The 10-K is from early 2026, so a later change at this site would not appear here.

  1. Planned or site prep
  2. Under construction
  3. Partly operating
  4. Operating
Build progress
OperatingCompany-reported

“lease operations at our Austin, Texas data center, which commenced in the second quarter of 2024” Core Scientific 10-K (fiscal year ended Dec. 31, 2025)

Financing
Not established
Planned capacity
Not established
In service
16 MW of infrastructure under the February 2024 CoreWeave contract

“to deliver 16 MW of infrastructure at our Austin, Texas facility” Core Scientific 10-K (fiscal year ended Dec. 31, 2025)

Next thing to watch
A filing giving current billing capacity at Austin.

“As of September 30, 2026, approximately 485 MW has commenced billing.” Core Scientific 10-Q (quarter ended Sept. 30, 2026)

Sources

On the Record

All CORZ filings

No Nexairi story linked yetLast reviewed Nov 20, 2026. Facts only.

Change history

Newest first. We never edit or delete an entry. When we re-read a source and correct ourselves, that gets its own entry, marked as our label changing, not as news from the site.

  1. Nov 20, 2026 · Added

    Added as Operating, from the 10-K (status as of Dec. 31, 2025).

    Core Scientific 10-K (fiscal year ended Dec. 31, 2025)

More Core Scientific sites

Other sites in Texas

See Austin data center on the globe with all 36 sites

Cite this

Nexairi, "Austin data center (Core Scientific)," AI Infrastructure Project Directory, last reviewed Nov 20, 2026. https://nexairi.com/on-the-record/directory/core-scientific-austin/

How labels are set: How we verify. Found a mistake? Tell us. Fixes are logged on the corrections page. Facts only. Not investment advice. Data is CC BY 4.0.