Muskogee expansion site (Polaris DS)
Core Scientific · Muskogee, OklahomaCore Scientific paid about $444 million in cash in August 2026 for a 40-acre site next to its Muskogee operations, with a substation and electric service agreements. The filing describes development rights, not construction. Its separate lease with AMD and another tenant covers about 530 MW across five sites, but the filing does not say which sites, and none of those leases had commenced as of September 30.
- Planned or site prep
- Under construction
- Partly operating
- Operating
- Build progress
- Planned or site prepCompany-reported
- Financing
- Not established
- Planned capacity
- up to 440 MW gross utility power, development rights
- In service
- Not established
- Purchase price paid
- $444.3 millionCompany-reported
- Cash paid for a 40-acre site with a substation and electric service agreements. Cash the filing says was paid to buy land or an asset. Not the cost of building on it.
- Next thing to watch
- A filing saying construction has started or a tenant is assigned to this site.
“development rights associated with electric service agreements providing for up to 440 MW of gross utility power capacity” Core Scientific 10-Q (quarter ended Sept. 30, 2026)
“development rights associated with electric service agreements providing for up to 440 MW of gross utility power capacity” Core Scientific 10-Q (quarter ended Sept. 30, 2026)
“The aggregate purchase price was approximately $ 444.3 million in cash” Core Scientific 10-Q (quarter ended Sept. 30, 2026)
Sources
- Core Scientific 10-Q (quarter ended Sept. 30, 2026) (SEC filing)
On the Record
- Nov 5, 2026 10-Q: Reported
- Nov 5, 2026 8-K: Reported
- Sep 10, 2026 8-K: Other
Change history
Newest first. We never edit or delete an entry. When we re-read a source and correct ourselves, that gets its own entry, marked as our label changing, not as news from the site.
Nov 19, 2026 · Added
Added as Planned or site prep.
More Core Scientific sites
See Muskogee expansion site (Polaris DS) on the globe with all 36 sites
Cite this
Nexairi, "Muskogee expansion site (Polaris DS) (Core Scientific)," AI Infrastructure Project Directory, last reviewed Nov 19, 2026. https://nexairi.com/on-the-record/directory/core-scientific-muskogee-expansion/
How labels are set: How we verify. Found a mistake? Tell us. Fixes are logged on the corrections page. Facts only. Not investment advice. Data is CC BY 4.0.