Fermi's big deal is still a maybe
Its own quarterly report calls the 600 MW deal a letter of intent. The clock runs out Dec. 31.
Hey friends. It's been a few weeks since the last Dispatch, so this one catches up.
The theme is the gap between a headline and a signature. Fermi says a big cloud company signed up for 600 megawatts of power in Texas. Its own quarterly report calls the deal a letter of intent, which means nobody's locked in yet. There's a Dec. 31 deadline, and you can watch it with us.
Data centers — Fermi's 600-megawatt deal is still a maybe
What happened: Fermi America is planning a huge data center campus called Project Matador in Carson County, Texas. On Nov. 12 it said an unnamed hyperscaler (one of the giant cloud companies, like Amazon or Microsoft) had signed up for 600 megawatts of power there. The results release lists a $200 million prepayment agreement and a $15 million early construction deal.
Here's the catch. Fermi's 10-Q, the quarterly report it files with the SEC, came out the same day. It calls the underlying deal a non-binding letter of intent. Neither side is bound yet. The release itself says both sides "continue to work toward a definitive long-term lease." Neither filing says how much of the $200 million has been paid. The site's earlier tenant lease, with TensorWave, ended on Nov. 10.
So why does the paperwork matter? Fermi leases the land from the Texas Tech University System. Texas Tech has to issue a notice to proceed by Dec. 31, or it "may terminate the lease." That notice depends on Fermi signing a lease with a first tenant for at least 200 megawatts. Then there's a second clock: Fermi's turbine financing counts it as a default if Fermi hasn't closed full financing for phase one by Feb. 10, 2027. As of the 10-Q, it hadn't.
Why it matters: A prepayment and a press release can look like a done deal. If your firm sells to, lends to or builds for a project like this, the signed lease is what tells you the money is real.
What to watch: An 8-K (the form companies file for big news) announcing a signed hyperscaler lease, or an extension from Texas Tech, before Dec. 31. If neither shows up, the land lease is at risk.
From Nexairi
Nvidia CEO Jensen Huang resigns: what the filing leaves out — Latest reporting
Nvidia's filing named an interim CEO and a new chair but gave no reason for the exit. We laid out what it says, what it skips and why the Nov. 17 earnings were the first real test.
Loudoun's data center pause: why the legal clock keeps running — Latest reporting
Loudoun County, Va., paused its board's final votes on data centers and substations (the sites that step power down for local lines) for up to 12 months. State law still gives each application a one-year clock. Staff say at least nine may run out first.
Firm vs non-firm data center power: New England's proposal — Beyond the Promise
ISO New England, which runs the region's grid, proposed three ways to hook up a data center of 50 megawatts or more. Under two of them, the data center can be told to cut back at $250 per megawatt-hour.
On the Record
Three filings worth a look since the last issue.
Alphabet · 424B5 · Nov 19 — SEC filing
Google's parent filed a preliminary prospectus (the sales document for a bond deal) to sell notes in Canadian dollars. The amounts and rates are still blank.
NRG · 8-K · Nov 12 — SEC filing
NRG agreed to sell nine subsidiaries to an affiliate of LS Power for $4.0 billion in cash. It expects to close in 2027, after antitrust review and sign-off from federal and New York energy regulators.
Southern Co · 424B2 · Nov 13 — SEC filing
Southern sold $1.75 billion of equity units, a bond bundled with a promise to buy shares later. The money goes first to older debt, and data centers show up in the documents we checked only as a risk.
Outside Nexairi
Nvidia beat estimates in its first report without Huang — CNBC
Revenue hit $115.84 billion against a $109.10 billion estimate. The stock still fell 2.89% Wednesday, and the board says it won't reinstate him.
Anthropic's IPO raised $81.3 billion — CNBC
That tops SpaceX's initial raise. The report doesn't say how much of it will go to chips and data centers.
Utilities want data centers locked into long grid contracts — Latitude Media
Filings at FERC, the federal energy regulator, would have data centers commit to paying for grid upgrades for 10 to 20 years before they're built.
Deeper Read
Data center slowdown would raise risks for utility investments — Utility Dive
An Orennia report estimates 191 gigawatts of planned data center capacity faces new risk after the midterms, mostly in Texas, Ohio and Georgia.