Does "connected" mean the same thing for every data center?

Not under a New England proposal. It describes three ways to connect a large data center, and two can be told to cut back.

On November 13, ISO New England said it had jointly filed a large-load proposal with federal regulators. The other filers were the New England Power Pool and the transmission owners' administrative committee. The ISO's information summary defines a "large load" as one customer at a single site with a gross peak demand of 50 megawatts or more, connecting at more than 60 kilovolts. The summary says some existing and critical loads are exempt. An existing site becomes a large load if its peak demand rises by 50 megawatts or more from its exempt level as of June 18, 2026.

The same summary explains why the filing exists. Federal regulators issued a show-cause order on large loads on June 18, and the ISO was given until November 16 to file its own design. So this is New England's answer to a question FERC asked.

What are the three proposed services?

The ISO's summary names them Firm, Interim and Non-Firm Contract Demand Service. A customer can combine them to serve one site.

Question Firm Interim Non-firm
Priority Same as other firm loads Not firm Not firm
What comes first All network upgrades finished and new capacity designated Offered before upgrades are done or the new-capacity rule is met No new capacity designated. Studies reflect the load's flexibility, which may mean fewer upgrades
How long Permanent, for a fixed contracted amount of megawatts Temporary: up to 7 years or the time to finish upgrades, whichever is longer Permanent
Can be told to cut back at $250/MWh Not named in the ISO's account Yes Yes

Sources: ISO information summary (updated November 9) and ISO Newswire (November 13). All terms are proposed.

The firm service is the one that carries a requirement. The summary says large loads must "bring your own new capacity," meaning new power supply matched to the new demand. The ISO also describes interim service as its own offering, not a limited mode of firm service.

Here is how the pieces could fit together. Suppose a developer wants a 100-megawatt campus. It could request firm service and wait for the upgrades and new supply that firm service requires. In the meantime it could take interim service, which the summary says is provided for the amount of firm service requested until the designated new capacity is operating. Or it could choose non-firm service and accept being told to cut back. This is an illustration of the structure, not a described customer.

What does "told to cut back" mean at $250/MWh?

The ISO says non-firm and interim customers would be re-dispatched when local prices reach $250 per megawatt-hour, meaning they cut use or add eligible generation.

Keep the units straight. A megawatt is a rate of power, like a car's speed. A megawatt-hour is an amount of energy, like miles driven. So $250/MWh is a price. It does not mean a 250-megawatt cut.

The ISO adds that the region crosses that price in only about 1% of hours. That is a regional figure. The trigger applies in the customer's own area, and the announcement we read does not define that area. How often it would bind at a given site is not shown.