IREN's earnings release says its more than $4 billion revenue target is "fully contracted and fully funded." The same release moves the date for reaching that target from the end of 2026 to January 2027.

Both statements can hold. They answer different questions. Picture a project tracker with two columns, "money lined up" and "open for customers." The word "funded" sits in the first column and the new date sits in the second. A footnote tells you what filled the first one.

IREN sells access to AI computing power and also mines bitcoin. The release lists Microsoft and NVIDIA among its customers. The numbers below come from the copy of the release filed with the SEC.

What does "fully funded" mean in IREN's release?

IREN defines "fully funded" in footnote 5. Four listed sources cover the remaining building and chip costs of one program, if funding conditions are met.

Here is the footnote's own wording:

"'Fully funded' means these sources cover the remaining capex from September 30, 2026, including data centers and GPUs, for the 0.3GW (IT) program that supports the more than $4 billion ARR target, subject to satisfaction of the conditions to funding under committed financing facilities, including conditions to the release of escrowed proceeds and applicable availability periods."

"Capex" is spending on buildings and equipment. A GPU is a chip that runs AI work. "ARR" is annualized run-rate revenue, covered below. The "0.3GW (IT)" is the program's size, measured in the power the computing equipment uses.

The footnote counts four sources as of September 30. Each one carries a different catch.

Source countedPlain meaningWhat the release says holds it back
Cash and cash equivalentsMoney IREN has nowNothing stated
Restricted cashCash held in escrow under IREN's loan and letter-of-credit arrangementsIt "remains subject to contractual limits on withdrawal or use"
Undrawn committed GPU financing facilitiesLoans lenders agreed to make that IREN hasn't borrowed yetThe footnote's "conditions to funding" and "availability periods"
Contracted customer prepayments not yet receivedMoney customers agreed to pay ahead of deliveryNot yet in IREN's hands

Only the first row is money IREN can spend today with no strings. The other three are real commitments, and each has a step still to finish.

What is inside the $15 billion plan, and what is still a target?

IREN plans $15 billion of remaining spending in its 2027 fiscal year. Its release covers $9 billion with committed sources and calls the other $6 billion a target.

LineAmountHow the release describes it
Remaining planned capex in fiscal 2027, counted from September 30$15 billionFootnote 11: the figure includes data centers and GPUs
Cash and committed GPU financing and prepayments$9 billionUses the footnote 5 definition above
Target GPU financing, prepayments, data center financing and other corporate level sources$6 billionDescribed as "subject to market conditions, to drive future capacity targets"

Our arithmetic: $9 billion is 60% of the plan and $6 billion is 40%.

The $6 billion is tied to future capacity targets. One is 0.8 gigawatts of data center capacity by the end of calendar 2027, which a second footnote says "may require additional capex in FY27." So the $6 billion looks like expansion money rather than a gap in the $4 billion program, though the release doesn't say so in those words.

The release does not say what the 0.3-gigawatt program costs, so the filing can't show whether $9 billion matches it. The $9 billion line carries the same footnote as the "fully funded" claim. That points to one pool of money, but it is our reading and not IREN's statement.

For another big number that depends on how it is defined, see our read of Anthropic's $518 billion plan.

Why did the date move, and to when?

IREN moved its target from the end of 2026 to January 31, 2027. It says the date may slip to the end of February after a customer-requested design change.

The release blames "a customer-requested change and supplier timing." Co-CEO Daniel Roberts put it this way: "after a customer-requested design change and supplier timing moved it from year-end; it may extend to the end of February."

Reuters, in a report posted on Euronext's site, said the customer was Microsoft and that it asked for network-design changes. Reuters also reported that IREN said the delay would not result in financial penalties.

The release itself lists a related risk. The timing of commissioning, testing and customer acceptance "may result in delay credits or other reductions in payments under our customer contracts." That reads as a general risk warning. We found nothing in the release saying any credits are owed.