Lake Mariner Data Campus
TeraWulf · Barker, New YorkTeraWulf says it has energized 102 MW of critical IT capacity for HPC customers at a former coal plant site, next to 145 MW of older bitcoin-mining capacity. It targets about 500 MW gross by early 2027. The sections we read do not tie any financing to this site.
- Planned or site prep
- Under construction
- Partly operating
- Operating
- Build progress
- Partly operatingCompany-reported
- Financing
- Not established
- Planned capacity
- about 500 MW gross, expected energized by early 2027
- In service
- 102 MW critical IT for HPC, energized
- Next thing to watch
- A filing showing HPC capacity energized beyond 102 MW.
“had energized 102 critical IT MW of HPC leasing capacity at the Lake Mariner Data Campus” TeraWulf 10-Q (quarter ended Sept. 30, 2026)
“approximately 500 MW of aggregate gross capacity expected to be energized by early 2027” TeraWulf 10-Q (quarter ended Sept. 30, 2026)
“the Lake Mariner Data Campus had 102 MW of energized critical IT HPC capacity” TeraWulf 10-Q (quarter ended Sept. 30, 2026)
Sources
- TeraWulf 10-Q (quarter ended Sept. 30, 2026) (SEC filing)
On the Record
- Nov 6, 2026 10-Q: Reported
- Nov 6, 2026 8-K: Reported
- Nov 4, 2026 8-K: Agreement disclosed
Change history
Newest first. We never edit or delete an entry. When we re-read a source and correct ourselves, that gets its own entry, marked as our label changing, not as news from the site.
Nov 19, 2026 · Added
Added as Partly operating.
More TeraWulf sites
Other sites in New York
See Lake Mariner Data Campus on the globe with all 36 sites
Cite this
Nexairi, "Lake Mariner Data Campus (TeraWulf)," AI Infrastructure Project Directory, last reviewed Nov 19, 2026. https://nexairi.com/on-the-record/directory/terawulf-lake-mariner/
How labels are set: How we verify. Found a mistake? Tell us. Fixes are logged on the corrections page. Facts only. Not investment advice. Data is CC BY 4.0.