Justified Data Campus
TeraWulf · Hawesville, KentuckyTeraWulf bought a former industrial site and signed leases with Anthropic for about 401 MW. On Nov. 4 it said Google provides credit support for debt financing it still describes as anticipated. That is a backstop for a loan that has not been reported closed. Fluor, the contractor, says early works construction has begun. Initial capacity is expected in late 2027.
- Planned or site prep
- Under construction
- Partly operating
- Operating
- Build progress
- Planned or site prepCompany-reported
- Financing
- Financing announcedCompany-reported
- Planned capacity
- about 401 MW critical IT, leased to Anthropic
- In service
- Not established
- Next thing to watch
- The project debt financing closing, or construction beyond early works confirmed in a company filing.
“Early works construction has already begun.” Fluor release via Business Wire (Nov. 4, 2026)
“provides contractual credit support for anticipated debt financing supporting TeraWulf's long-term Justified development.” TeraWulf 8-K Exhibit 99.1 (Nov. 4, 2026)
“lease agreements with Anthropic for approximately 401 MW of critical IT capacity” TeraWulf 10-Q (quarter ended Sept. 30, 2026)
“phased ready-for-service completions are expected to begin in late 2027 and continue through the second quarter of 2028.” TeraWulf 8-K Exhibit 99.1 (Nov. 4, 2026)
Sources
- TeraWulf 10-Q (quarter ended Sept. 30, 2026) (SEC filing)
- TeraWulf 8-K Exhibit 99.1 (Nov. 4, 2026) (SEC filing)
- Fluor release via Business Wire (Nov. 4, 2026) (Company release)
On the Record
- Nov 6, 2026 10-Q: Reported
- Nov 6, 2026 8-K: Reported
- Nov 4, 2026 8-K: Agreement disclosed
Change history
Newest first. We never edit or delete an entry. When we re-read a source and correct ourselves, that gets its own entry, marked as our label changing, not as news from the site.
Nov 20, 2026 · Changed on the ground
Financing label moved from not established to announced after reading TeraWulf's Nov. 4 8-K exhibit: Google signed credit support for anticipated debt financing. No loan is reported closed. This was published before our Nov. 19 add and we missed it then. Fluor's release says early works construction has begun, which stays within Planned or site prep. Data Center Dynamics reported on Nov. 20 that vertical construction started, citing a company LinkedIn post. We have not read that post, so build progress is unchanged.
TeraWulf 8-K Exhibit 99.1 (Nov. 4, 2026)Nov 19, 2026 · Added
Added as Planned or site prep.
See Justified Data Campus on the globe with all 36 sites