Richland Parish Units 1-4 (gas units for a new data center customer)

Entergy Louisiana · Louisiana

Entergy Louisiana asked state regulators in March 2026 to certify seven new gas units totaling 5,278 MW. Four of them, Richland Parish Units 1-4, would sit near the customer's site in north Louisiana. The filing says Entergy Louisiana signed power agreements for two new data centers there with subsidiaries of Meta Platforms, and it reports higher construction spending on the Richland Parish project. A settlement with regulators' staff recommends certification, and a decision is due in December 2026. The units have estimated in-service dates in 2030 and 2031, and the filing does not say which units serve which data center.

  1. Planned or site prep
  2. Under construction
  3. Partly operating
  4. Operating
Build progress
Planned or site prepCompany-reported

“by Entergy Louisiana on the Richland Parish Power Station Units 1-4 project” Entergy 10-Q (quarter ended Sept. 30, 2026)

Financing
Financing announcedCompany-reported

“Entergy Louisiana has used or expects to use the proceeds to finance construction of a portion or all of its capital plan, including the construction of any or all of the Richland Parish Units 1-4 project” Entergy 10-Q (quarter ended Sept. 30, 2026)

Planned capacity
5,278 MW across seven new gas units (four near the customer site)

“seven new combined cycle combustion turbine generation resources totaling 5,278 MW” Entergy 10-Q (quarter ended Sept. 30, 2026)

In service
Not established
Next thing to watch
The state commission's decision on the seven units, which the filing expects in December 2026.

“An LPSC decision is expected in December 2026.” Entergy 10-Q (quarter ended Sept. 30, 2026)

Sources

On the Record

All ETR filings

Read our coverageLast reviewed Nov 19, 2026. Facts only.

Change history

Newest first. We never edit or delete an entry. When we re-read a source and correct ourselves, that gets its own entry, marked as our label changing, not as news from the site.

  1. Nov 19, 2026 · Added

    Added as Planned or site prep, financing announced.

Other sites in Louisiana

See Richland Parish Units 1-4 (gas units for a new data center customer) on the globe with all 36 sites

Cite this

Nexairi, "Richland Parish Units 1-4 (gas units for a new data center customer) (Entergy Louisiana)," AI Infrastructure Project Directory, last reviewed Nov 19, 2026. https://nexairi.com/on-the-record/directory/entergy-richland-parish-units/

How labels are set: How we verify. Found a mistake? Tell us. Fixes are logged on the corrections page. Facts only. Not investment advice. Data is CC BY 4.0.