A data center needs local government approval before anyone can build it, and this week a court showed how fragile that approval can be. A Virginia judge ruled on Nov. 23 that the Botetourt County board of supervisors broke the state's Freedom of Information Act, the law that requires open meetings and public notice, when it approved a deal with Google's developer, Helio Capital LLC, on June 24, 2025, Cardinal News reported. The county, in the Roanoke area, sold Google about 312 acres for a planned campus of at least $3 billion, the Roanoke Rambler reports. The judge ordered the county to undo its actions since that meeting and ordered Helio Capital to stop construction. He also required a new public hearing that follows the law. The board voted 5-0 with no discussion after a closed session, according to the Rambler.
My read: this ruling is about notice, not about whether the campus is a good idea. The county's lawyer called the problems "technical." The judge wrote that technical violations are not excused. That is also why the project is not dead. The Rambler reports the county could hold a new hearing and vote again, or appeal. But the sequence is worth noticing. An approval a company relied on was reopened 17 months later, after crews had started grading the site. Anyone who supplies, lends against or plans around a project like this should ask which agreements depend on a vote that could be reopened this way.
The county spokesman said work could continue for several more days, possibly a week, while crews wind down and secure equipment. The board has not said whether it will appeal or hold another vote, and Google said it is "evaluating" the ruling. The next things to watch are a hearing date, an appeal filing or a new vote.