TSMC Arizona fabs

TSMC · Phoenix, Arizona

TSMC's annual report says its first Phoenix facility entered high volume production at the end of 2024, the second is under construction, and construction of a third began in 2025. The only dollar figure the filing ties to the Phoenix site is a U.S. government funding agreement of up to US$6.6 billion, which is an award, not money received or the cost of the project. We found no total project cost in the report. The annual report covers 2025, so the build label is as of that report.

  1. Planned or site prep
  2. Under construction
  3. Partly operating
  4. Operating
Build progress
Partly operatingCompany-reported

“Our first facility successfully entered high volume production at the end of 2024. Construction of our second facility is ongoing, and the construction of our third facility commenced in 2025” TSMC 20-F (fiscal year ended Dec. 31, 2025)

Financing
Agreement signed, not yet fundedCompany-reported

“the DOC agrees to award TSMC Arizona up to US$6.6 billion in direct funding related to TSMC Arizona's semiconductor manufacturing facilities in Phoenix, Arizona” TSMC 20-F (fiscal year ended Dec. 31, 2025)

Planned capacity
Not established
In service
Not established
Government funding agreed
Up to $6.6 billionCompany-reported
Direct funding the U.S. Department of Commerce agreed to award for the Phoenix facilities, under an agreement signed in November 2024. Funding a government agreed to award, usually paid in stages as milestones are met. Not all of it has been paid.

“the DOC agrees to award TSMC Arizona up to US$6.6 billion in direct funding related to TSMC Arizona's semiconductor manufacturing facilities in Phoenix, Arizona” TSMC 20-F (fiscal year ended Dec. 31, 2025)

Next thing to watch
A TSMC filing saying the second Phoenix facility has entered production.

Sources

No Nexairi story linked yetLast reviewed Nov 24, 2026. Facts only.

Change history

Newest first. We never edit or delete an entry. When we re-read a source and correct ourselves, that gets its own entry, marked as our label changing, not as news from the site.

  1. Nov 24, 2026 · Added

    Added as Partly operating, funding agreement signed.

See TSMC Arizona fabs on the globe with all 36 sites

Cite this

Nexairi, "TSMC Arizona fabs (TSMC)," AI Infrastructure Project Directory, last reviewed Nov 24, 2026. https://nexairi.com/on-the-record/directory/tsmc-arizona-phoenix/

How labels are set: How we verify. Found a mistake? Tell us. Fixes are logged on the corrections page. Facts only. Not investment advice. Data is CC BY 4.0.