PORTS-Pike Technology Campus

SB Energy · Pike County, Ohio

NVIDIA announced it will back the land, power and building shell for a campus SB Energy will build for OpenAI. The release does not say construction has started or that the credit support has been signed.

  1. Planned or site prep
  2. Under construction
  3. Partly operating
  4. Operating
Build progress
Planned or site prepCompany-reported

“The planned capacity is expected to come online in phases beginning in 2028.” NVIDIA release (Aug. 17, 2026)

Financing
Financing announcedCompany-reported

“NVIDIA to provide credit support on land, power and shell buildout to secure initial 4.25 IT-GW” NVIDIA release (Aug. 17, 2026)

Planned capacity
4.25 IT-GW initial deployment, planned

“The initial deployment is designed to support 4.25 IT-GW of AI factory capacity.” NVIDIA release (Aug. 17, 2026)

In service
Not established
Next thing to watch
A filing or release saying construction has started, or that the credit support was signed.

Sources

No Nexairi story linked yetLast reviewed Nov 17, 2026. Facts only.

Change history

Newest first. We never edit or delete an entry. When we re-read a source and correct ourselves, that gets its own entry, marked as our label changing, not as news from the site.

  1. Nov 17, 2026 · Our label changed

    Split the label in two: build progress is Planned or site prep; financing is Financing announced. Nothing new happened at the site.

    NVIDIA release (Aug. 17, 2026)
  2. Nov 16, 2026 · Added

    Added as Financing-related.

Other sites in Ohio

See PORTS-Pike Technology Campus on the globe with all 36 sites

Cite this

Nexairi, "PORTS-Pike Technology Campus (SB Energy)," AI Infrastructure Project Directory, last reviewed Nov 17, 2026. https://nexairi.com/on-the-record/directory/ports-pike-technology-campus/

How labels are set: How we verify. Found a mistake? Tell us. Fixes are logged on the corrections page. Facts only. Not investment advice. Data is CC BY 4.0.