Polaris Forge 1

Applied Digital · Ellendale, North Dakota

Applied Digital says the first two buildings at this campus are in operation and a third, adding 150 MW, is under construction with full readiness expected in calendar 2027. The 10-K says a subsidiary closed a $2.35 billion senior secured notes offering in November 2025, with proceeds meant for construction of the first two data centers here. The 10-Q itself does not name the tenant. The 10-K does (see the history entry).

  1. Planned or site prep
  2. Under construction
  3. Partly operating
  4. Operating
Build progress
Partly operatingCompany-reported

“we commenced operations at our first HPC data center at our Polaris Forge 1 campus in Ellendale, North Dakota” Applied Digital 10-Q (quarter ended Aug. 31, 2026)

Financing
Money drawn or receivedCompany-reported

“closed a $2.35 billion offering” Applied Digital 10-K (fiscal year ended May 31, 2026)

Planned capacity
third building adds 150 MW, expected ready for service in 2027

“Our third HPC building at our Polaris Forge 1 campus, which is expected to provide an additional 150MW of capacity, is currently under construction.” Applied Digital 10-Q (quarter ended Aug. 31, 2026)

In service
Not established
Debt issued
$2.35 billionCompany-reported
Senior secured notes offering closed by a subsidiary, for the campus's first two data centers. Notes or loans the filing says were issued. Borrowing for the site, not proof of how much was spent or built.

“closed a $2.35 billion offering” Applied Digital 10-K (fiscal year ended May 31, 2026)

Next thing to watch
A filing saying the third building is ready for service.

Sources

On the Record

All APLD filings

No Nexairi story linked yetLast reviewed Nov 20, 2026. Facts only.

Change history

Newest first. We never edit or delete an entry. When we re-read a source and correct ourselves, that gets its own entry, marked as our label changing, not as news from the site.

  1. Nov 20, 2026 · Our label changed

    Added the 10-K as a source. Financing moves from Not established to Money drawn or received: the 10-K says APLD ComputeCo closed a $2.35 billion notes offering to fund construction of the campus's first two data centers. The 10-K also names CoreWeave as the tenant, with 400 MW contracted across the campus. Nothing new happened at the site.

    Applied Digital 10-K (fiscal year ended May 31, 2026)
  2. Nov 19, 2026 · Added

    Added as Partly operating.

More Applied Digital sites

See Polaris Forge 1 on the globe with all 36 sites

Cite this

Nexairi, "Polaris Forge 1 (Applied Digital)," AI Infrastructure Project Directory, last reviewed Nov 20, 2026. https://nexairi.com/on-the-record/directory/applied-digital-polaris-forge-1/

How labels are set: How we verify. Found a mistake? Tell us. Fixes are logged on the corrections page. Facts only. Not investment advice. Data is CC BY 4.0.